Microsoft Dynamics 365 Fundamentals (ERP) — Question 86
A company creates a project plan in Dynamics 365 Project Operations.
The project plan must allow a project manager to:
• Track profitability,
• Collaborate on the work to be performed, and
• Allocate people to perform tasks.
You need to identify the project derivatives that the project plan must track.
Which three major project derivatives should the plan track? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
Answer options
- A. resourcing
- B. schedule updates
- C. invoicing
- D. cost
- E. scope
Correct answer: A, B, D
Explanation
The correct answers are A, B, and D because resourcing allows for tracking personnel allocation, schedule updates help monitor project timelines, and cost is essential for assessing profitability. Invoicing and scope do not directly contribute to tracking profitability, collaboration, or task allocation in the same way.