Microsoft Dynamics 365 Fundamentals (ERP) — Question 17

A company plans to implement Dynamics 365 Supply Chain Management.
The company wants shop floor workers to register their daily work by using the production floor execution interface.
Which two activities can employees perform by using the tool? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.

Answer options

Correct answer: B, D

Explanation

The correct answers are B and D because employees can log scrap quantities as part of their production activities and clock in and out to track their work hours. Options A and C are incorrect as those tasks typically require different permissions and tools not available in the production floor execution interface.