You use the master planning module for Dynamics 365 Supply Chain Management.
Planned production orders have been created.
Several sales orders are canceled in response to concerns about recent online reviews of a product.
You need to enable the appropriate action message.
Which action message should you enable?
Answer options
- A. Increase
- B. Postpone
- C. Decrease
- D. Derived actions
- E. Advance
Correct answer: C
Explanation
The correct action message to enable is 'Decrease' because canceling sales orders indicates a reduced demand for the product, necessitating a decrease in production. The other options, such as 'Increase' or 'Advance', do not align with the need to lower production levels in response to decreased sales.