Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert — Question 79
You are the lead product design engineer at a plastics manufacturing company.
You implement a new process that uses a single tool to produce three finished goods at the same time.
You need to set up the planning item number and formula to correctly to manufacture the three items.
Which three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
Answer options
- A. Create item number for planning item and the associated formula.
- B. Specify each of the finished good items as co-products.
- C. Add minimum and maximum quantities on formula.
- D. Assign co-products to the formula.
- E. Add a coverage group to the formula.
Correct answer: A, B, D
Explanation
The correct actions are to create an item number and formula (A), specify the finished goods as co-products (B), and assign those co-products to the formula (D). Options C and E, while they may be relevant in certain contexts, do not directly address the requirement to set up the planning item number and formula for producing co-products.