Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert — Question 76
A company uses Dynamics 365 Supply Chain Management for Process manufacturing.
You are reviewing the planned production orders for the next two weeks. There are several production orders for the same product. One order is scheduled to run the week after another order.
You need to optimize the planned production orders.
What should you do?
Answer options
- A. In Planned orders, combine the production orders.
- B. Rerun master planning. Select the dynamic plan with a coverage time fence of two weeks.
- C. Firm the orders.
- D. Rerun master planning. Select the static plan with a coverage time fence of two weeks.
Correct answer: D
Explanation
The correct answer is D because rerunning master planning with a static plan allows for better optimization of production schedules by adhering to fixed parameters. Option A is incorrect as simply combining orders may not address scheduling efficiency. Option B may not provide the same level of optimization as a static plan in this scenario, and option C does not contribute to optimizing the planned production orders.