Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert — Question 242
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
Create a vendor warehouse for the subcontracting vendor.
Create a vendor resource and add it to a new work cell for outsource painting.
Create a production flow transfer activity and specify the vendor warehouse as the target warehouse.
Does the solution meet the goal?
Answer options
- A. Yes
- B. No
Correct answer: B
Explanation
The solution does not meet the goal because simply creating a vendor warehouse and a vendor resource does not adequately establish a subcontracting activity for the painting service. A more comprehensive approach is needed that includes defining the actual subcontracting process and ensuring proper integration with Lean processes, which is not achieved with the current solution.