You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item.
This item has the following Lean setup:
• The setup uses a Lean schedule group with a throughput ratio = 2.
• The process activity tied to production flow has the following runtime activity times: time = 3 min, per quantity = 1.
• The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8 hour day).
• The throughput is 10 per hour.
You need to set up a Discrete operation to mirror the item’s production flow activity.
What should you do?
Answer options
- A. Create a route with a runtime = 1, a process quantity = 10, and the operation’s hours/time = 1.
- B. Create a route with a runtime = 1, a process quantity = 1, and the operation’s hours/time = 0.0167 (e.g. 1 hour/60 minutes).
- C. Create a route with a runtime = 10, a process quantity = 6, and the operation’s hours/time = 1.
- D. Create a route with a runtime = 1, a process quantity = 6, and the operation’s hours/time = 1.
Correct answer: C
Explanation
The correct answer is C because it accurately reflects the runtime needed to match the Lean setup's parameters, specifically aligning with the throughput and production flow requirements. Options A, B, and D do not align with the necessary runtime or process quantities to effectively mirror the Lean operation, making them incorrect choices.