Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert — Question 207
You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item.
This item has the following Lean setup:
• The setup uses a Lean schedule group with a throughput ratio = 2.
• The process activity tied to production flow has the following runtime activity times: time = 3 min, per quantity = 1.
• The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8 hour day).
• The throughput is 10 per hour.
You need to set up a Discrete operation to mirror the item’s production flow activity.
What should you do?
Answer options
- A. Create a route with a runtime = 1, a process quantity = 10, and the operation's hours/time = 1.
- B. Create a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 1.
- C. Create a route with a runtime = 1, a process quantity = 6, and the operation’s hours/time = 0.0167 (e.g. 1 hour/60 minutes).
- D. Create a route with a runtime = 1, a process quantity = 1, and the operation's hours/time = 1.
Correct answer: B
Explanation
The correct answer is B, as it aligns with the process flow and runtime requirements needed to mirror the Lean setup. In this case, a runtime of 6 provides the necessary processing time to match the original activity time of 3 minutes per quantity of 1 when converting to a Discrete operation. The other options either do not meet the required runtime or misalign the process quantity, making them unsuitable for the task.