Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert — Question 150
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing company produces electronic components and devices.
The company has scheduling issues related to using working time calendars in manufacturing.
You need to ensure that the working time calendar is used when manufacturing jobs are scheduled.
Solution: Enable automatic consumption of run time.
Does the solution meet the goal?
Answer options
- A. Yes
- B. No
Correct answer: B
Explanation
The solution does not meet the goal because enabling automatic consumption of run time does not directly address the scheduling issues related to working time calendars. The correct approach would involve ensuring that the working time calendars are effectively integrated into the scheduling process, which this solution fails to accomplish.