A company produces paints and assembles bicycle frames.
You must account for paint drying time before assembly operations can begin.
You need to set up the operation to encompass queue times.
Which two options can you use? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
Answer options
- A. Build capabilities for each resource related to color.
- B. Enter a value in the queue time after field for the painting operation.
- C. Enter a value in the transit time on the painting operation.
- D. Make a resource group for each size and color and assign that group to the operation.
- E. Enter a value in the queue time before field for the assembly operation.
Correct answer: B, E
Explanation
The correct answers are B and E because they directly address the need to incorporate queue times in the operations. Option B allows for specifying the time required after painting before moving to assembly, while option E ensures that the assembly operation waits adequately until the paint is dry. The other options do not specifically address the queue time requirements.