Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert — Question 120

You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.

A machine in the facility is defective and must be closed for repairs for the next two days.

You need to configure the resource calendar to close the resource for production for the next two days.

What should you do?

Answer options

Correct answer: A

Explanation

The correct answer is A because configuring a calendar deviation specifically targets the resource in question, allowing for a temporary closure without affecting the entire production calendar. Options B and D would impact more resources than necessary, while option C does not specify the appropriate method to implement the closure for a limited duration.