Microsoft Dynamics 365 Supply Chain Management — Question 81

A company is implementing Dynamics 365 Supply Chain Management. The company uses weighted average date as its costing model.

The controller requires the cost on the receipts to be used throughout the month until the month-end close procedure is run.

You need to configure the item model group.

Which two actions should you perform? Each correct answer presents part of the solution. (Choose two.)

NOTE: Each correct selection is worth one point.

Answer options

Correct answer: A, B

Explanation

Selecting option A to clear the Marking checkbox prevents the marking of transactions for inventory valuation, which is necessary for maintaining consistent costs. Option B is correct as selecting the Include physical value checkbox allows for the inclusion of physical inventory values in the costing model. The other options do not align with the requirement to maintain consistent costs throughout the month.