Microsoft Dynamics 365 Supply Chain Management — Question 57
A company uses Dynamics 365 Supply Chain Management.
Three assets at a single location all need the same tune-up. A single worker can complete all three tune-ups. The worker’s hours must be allocated to each asset.
You need to configure the system for the worker.
Which configuration should you use?
Answer options
- A. Configure the operations resource and set it to human resource.
- B. Configure work line details.
- C. Create a consumption registration for the expenses.
- D. Create one work order and split hours by work order job.
Correct answer: D
Explanation
The correct answer is D because creating one work order and splitting the hours allows for an efficient allocation of the worker's time across all three assets while maintaining proper tracking. Options A, B, and C do not address the requirement of distributing hours among multiple assets effectively.