Microsoft Dynamics 365 Supply Chain Management — Question 54

A company uses Dynamics 365 Supply Chain Management.

Three assets at a single location all need the same tune-up. A single worker can complete all three tune-ups. The worker’s hours must be allocated to each asset.

You need to configure the system for the worker.

Which configuration should you use?

Answer options

Correct answer: D

Explanation

Creating three separate work orders (D) is the correct approach because it allows clear tracking of the worker's time and tasks for each asset. Configuring a job card (B) or labor standards (C) does not directly address the need to allocate time to multiple assets, while a consumption registration (A) is not relevant to the worker's time allocation.