Microsoft Dynamics 365 Supply Chain Management, Manufacturing — Question 5
A company wants to account for the time to set up a machine to manufacture a new part.
You need to set up the costing calculations in the system.
Which three calculation group warnings can you set up? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
Answer options
- A. No consumption
- B. No cost price
- C. No BOM
- D. No resources
- E. No route
Correct answer: B, C, E
Explanation
The correct answers are B, C, and E because they represent critical elements in the costing process. 'No cost price' indicates that there is no pricing data available, 'No BOM' signifies the absence of a Bill of Materials, and 'No route' shows that there is no defined production route. Options A and D are not applicable in this context as they do not directly impact the setup costing calculations.