Microsoft Dynamics 365 Supply Chain Management, Manufacturing — Question 24

You have a product that can be manufactured on two different production lines in the same warehouse. You create resources and then create individual input locations for the resources. You create two routes. Each route uses different resources.
Materials are staged for consumption in different locations based on the resources being utilized for production.
You need to set up the formula to consume the goods from the correct line-side location.
What should you do?

Answer options

Correct answer: B

Explanation

The correct answer is B because selecting resource consumption and the operation for each line directly addresses the need to consume goods from the correct line-side location based on the resources. The other options either focus on warehouse selection, planning groups, or site specification, which do not specifically manage resource consumption for the distinct production lines.