Microsoft Dynamics 365 Supply Chain Management, Manufacturing — Question 19

You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.
A machine in the facility is defective and must be closed for repairs for the next two days.
You need to configure the resource calendar to close the resource for production for the next two days.
What should you do?

Answer options

Correct answer: D

Explanation

The correct answer is D because selecting 'Calendar deviations' allows you to specifically close the resource's calendar for the designated two days without affecting the entire resource group or production calendar. Options A and B would not close the specific resource but rather impact multiple resources or the overall production calendar. Option C does not provide the necessary option to set deviations for just that resource.