Microsoft Dynamics 365 Supply Chain Management, Manufacturing — Question 12

A chemical manufacturing company uses Dynamics 365 Supply Chain Management. A batch of material has a quality issue and must be reworked.
You need to create the rework order the production.
Which three options must be set? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.

Answer options

Correct answer: A, B, D

Explanation

The correct answers are A, B, and D because reserving the reworked inventory ensures it is accounted for during production, setting the item as a Formula production type is necessary for handling chemical processes, and designating the batch order as a rework batch identifies it correctly in the system. Options C and E are irrelevant for creating the rework order as they do not address the necessary settings for reworking the batch.