Microsoft Dynamics 365 Core Finance and Operations — Question 30

You plan the migration from a Dynamics AX 2012 to a Dynamics 365 Finance environment.
You are tasked with overseeing and planning a cutover to guarantee a smooth experience for end users during the cutover. You perform a basic data upgrade validation.
You need to perform a cutover.
Which three tasks must you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.

Answer options

Correct answer: B, D, E

Explanation

The correct answers are B, D, and E. Copying the upgraded database to production (B) is essential to make the new system operational. Performing a smoke test (D) ensures that critical functionalities are working post-migration. Completing application setup tasks (E) is necessary to configure the new environment properly. Options A and C do not directly relate to the cutover process.