Microsoft Dynamics 365 Field Service — Question 102

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

You are implementing Microsoft Dynamics 365 Field Service for a health care institution. Each day, the institution receives a large number of appointment requests for pediatricians.

You have the following requirements:
• create a daily schedule for pediatricians with a frequency of 30 minutes for each slot.
• provide a full-day schedule with start times and end times.

Solution: You create a fulfillment preference with time group details with a duration of 30 minutes for the whole day, associate it to a requirement, and then book the requirement with the schedule assistant.

Does this meet the goal?

Answer options

Correct answer: A

Explanation

The solution correctly creates a fulfillment preference with a 30-minute time group for the entire day, which aligns with the scheduling requirements. Option B is incorrect because the proposed solution effectively meets the goals set for scheduling pediatrician appointments.