Implementing Analytics Solutions Using Microsoft Fabric — Question 18

You have a Fabric tenant that contains a data pipeline.
You need to ensure that the pipeline runs every four hours on Mondays and Fridays.
To what should you set Repeat for the schedule?

Answer options

Correct answer: C

Explanation

The correct answer is C, as setting the schedule to 'Weekly' allows the pipeline to run on specified days, like Mondays and Fridays, at the desired interval. Options A, B, and D do not meet the requirement of running specifically every four hours on those two days.