Windows Server Administration Fundamentals — Question 18
You are the Microsoft Project Server administrator for your company. You have recently upgraded the hardware of your Microsoft Project Server farm. You and the project managers in your company believe that it will be much faster. You have now created performance logs to measure the throughput of the new server configuration to compare to past performance. What is this process called?
Answer options
- A. Performance baseline creation
- B. Step funding
- C. Before and after snapshot
- D. Performance measurement
Correct answer: A
Explanation
The correct answer is A, Performance baseline creation, as it involves establishing a reference point for performance to compare future metrics against. Options B and C do not specifically relate to measuring server performance, while D, Performance measurement, is a broader term that does not specifically denote the act of creating a baseline for comparison.