A switch is claimed in a Mist organization using the activation code.
What are two possible device states that the switch will have in this scenario? (Choose two.)

Answer options

Correct answer: B, D

Explanation

The correct answers are B (Inactive) and D (Unassigned) because when a switch is initially claimed, it may not yet be fully operational or assigned to a specific location within the network. Options A (Connected) and C (Active) imply that the switch is fully functional and operational, which is not the case immediately after claiming it.