JNCIS-ENT: Juniper Networks Certified Specialist – Enterprise Routing and Switching (2021) — Question 86
Which two statements are correct about a policy scheduler? (Choose two.)
Answer options
- A. A policy scheduler can only be applied when using the policy-rematch feature.
- B. A policy scheduler can be dynamically activated based on traffic flow volumes.
- C. A policy scheduler can be defined using a daily schedule.
- D. A policy scheduler determines the time frame that a security policy is actively evaluated.
Correct answer: C, D
Explanation
Options C and D are correct because a policy scheduler allows for the definition of schedules, including daily intervals, and it specifies the period during which a security policy is assessed. Options A and B are incorrect as they do not accurately reflect the capabilities of a policy scheduler in terms of its application or activation based on traffic.