You are performing a risk assessment for a network design.
Which statement is true in this scenario?
Answer options
- A. Some risks can be safely ignored.
- B. The likelihood of a risk occurring should not be considered.
- C. A network must be designed for an uptime of five nines.
- D. All identified risks must have a mitigation plan in place.
Correct answer: A
Explanation
The correct answer is A because while some risks are significant and must be addressed, others may not pose enough threat to warrant action. Option B is incorrect as assessing the likelihood of risks is crucial for prioritization. Option C may not always be feasible depending on the organization's requirements and resources. Option D is also incorrect since not every risk requires a mitigation plan if it is deemed negligible.