JNCIE-ENT: Juniper Networks Certified Expert – Enterprise Routing and Switching — Question 12

You are performing a risk assessment for a network design.
Which statement is true in this scenario?

Answer options

Correct answer: A

Explanation

The correct answer is A because while some risks are significant and must be addressed, others may not pose enough threat to warrant action. Option B is incorrect as assessing the likelihood of risks is crucial for prioritization. Option C may not always be feasible depending on the organization's requirements and resources. Option D is also incorrect since not every risk requires a mitigation plan if it is deemed negligible.