ISTQB Certified Tester Foundation Level v4.0 — Question 64

Consider an estimation session in which a six-member Agile team (Mempb1, ..., Memb6) uses the planning poker technique to estimate a user story (in story points). The team members will use a set of cards with the following values: 1, 2, 3, 5, 8, 13, 21. Below is the outcome of the first round of estimation for this session:

Memb1 = 3 Memb2 = 3 Memb3 = 3
Memb4 = 21 Memb5 = 3 Memb6 = 1

Which of the following answers BEST describes how the estimation session should proceed?

Answer options

Correct answer: D

Explanation

The correct answer is D because it encourages team members to discuss their differing estimates, which can lead to a better understanding of the user story and potentially align their views. Options A and C suggest mathematical approaches that do not foster discussion, while B simply calls for more rounds without addressing the underlying reasons for discrepancies in estimates.