ISTQB Certified Tester Foundation Level v4.0 — Question 56

Determining the schedule for each testing activity and test milestones for a test project, using activity estimates, available resources, and other constraints is a typical task performed during:

Answer options

Correct answer: D

Explanation

The correct answer is D, Test planning, as this phase involves scheduling and organizing all testing activities. Test execution refers to carrying out the tests, Test design pertains to creating the test cases, and Test analysis focuses on evaluating the test results, none of which directly involve scheduling activities.