ISTQB CT-TAE – Certified Tester Test Automation Engineer — Question 42

You are planning the pilot for an in-house developed Test Automation solution (TAS).
Which two of the following would be important steps to take as part of the planning process? a) Review your organisation's current projects and identify which one would be most suitable to pilot the TAS. b) Ensure that the developers will provide the necessary commitment for the TAS deployment activities. c) Run a series of training workshops for new users of the TAS before they are asked to use it. d) Develop a project plan for the pilot and reserve the necessary budget and resources for its implementation. e) Ask the developers to provide any missing functionality during the deployment activities.

Answer options

Correct answer: A

Explanation

Choosing the right project for the pilot is essential to ensure the TAS is tested in a suitable environment, while securing developer commitment is crucial for successful deployment. The other options, although important, either focus on training or resource management, which are secondary to selecting an appropriate project and ensuring team buy-in.