ISQI Certified Tester Foundation Level — Question 59

Which of the following metrics could be used to monitor progress along with test preparation and execution?

Answer options

Correct answer: C

Explanation

The correct answer is C, as tracking the failure rate in completed testing provides insight into the effectiveness and quality of the tests executed. Options A and B do not indicate the current status of testing but rather the planned scope, while option D focuses on resources rather than the quality of the outcomes.