ISQI Certified Tester Foundation Level — Question 59
Which of the following metrics could be used to monitor progress along with test preparation and execution?
Answer options
- A. The total number of tests planned
- B. The total number of requirements to be tested
- C. The failure rate in testing already completed
- D. The number of testers used for test execution so far
Correct answer: C
Explanation
The correct answer is C, as tracking the failure rate in completed testing provides insight into the effectiveness and quality of the tests executed. Options A and B do not indicate the current status of testing but rather the planned scope, while option D focuses on resources rather than the quality of the outcomes.