ISQI Certified Tester Foundation Level — Question 35

Which of the following are 'Exit Criteria?'

Answer options

Correct answer: A

Explanation

The correct answer is A, as Exit Criteria are defined as the conditions that must be met before a project phase can be considered complete. The other options describe various aspects of software development but do not specifically relate to the conditions for exiting a phase.