ISQI Certified Tester Foundation Level — Question 24
Typically, exit criteria may consist of:
Answer options
- A. Defining the amount, level of detail structure, and templates for the test documentation.
- B. Estimates of defect density or reliability measures.
- C. Adequacy of the test approaches taken.
- D. Discussions on disaster recovery.
Correct answer: B
Explanation
The correct answer, B, refers to specific metrics that assess the quality of the software, such as defect density and reliability, which are crucial for determining when testing can be deemed successful. Options A and C focus on documentation and testing strategies, which are important but do not directly serve as exit criteria. Option D, while relevant to overall project management, does not pertain to the completion of testing activities.