ISQI Certified Tester Foundation Level — Question 20

Which of the following risks represents the highest level of risk to the project?

Answer options

Correct answer: B

Explanation

Option B has a likelihood of failure of 10% with a potential cost impact of $500,000, leading to a risk value of $50,000. This is higher than the other options, as their calculated risk values are lower due to either lower likelihoods or lower potential impacts. Thus, option B represents the highest level of risk to the project.