Systems Security Certified Practitioner (SSCP) — Question 136
Which of the following is less likely to be included in the change control sub-phase of the maintenance phase of a software product?
Answer options
- A. Estimating the cost of the changes requested
- B. Recreating and analyzing the problem
- C. Determining the interface that is presented to the user
- D. Establishing the priorities of requests
Correct answer: A
Explanation
Estimating the cost of changes is typically not a focus during the change control sub-phase, which is more concerned with identifying and analyzing issues. In contrast, recreating and analyzing the problem, determining user interface changes, and establishing request priorities are essential activities directly related to managing changes effectively.