CISSP – Information Systems Security Management Professional (ISSMP) — Question 31
What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?
Answer options
- A. Scope Verification
- B. Project Management Information System
- C. Integrated Change Control
- D. Configuration Management System
Correct answer: D
Explanation
The Configuration Management System is responsible for managing changes to the project scope by evaluating, testing, and documenting those changes. Scope Verification focuses on confirming that the project deliverables meet the requirements, while the Project Management Information System and Integrated Change Control serve different roles in project management that do not specifically handle the documentation of scope changes.