CISSP – Information Systems Security Architecture Professional (ISSAP) — Question 90

Which of the following plans is a comprehensive statement of consistent actions to be taken before, during, and after a disruptive event that causes a significant loss of information systems resources?

Answer options

Correct answer: A

Explanation

The correct answer is A, as a Disaster recovery plan specifically focuses on restoring IT operations after a disruptive event. While B, C, and D also relate to managing disruptions, they encompass broader aspects of preparedness and continuity rather than a targeted approach to recovering information systems.