Certified Cloud Security Professional (CCSP) — Question 459
What is one of the reasons a baseline might be changed?
Answer options
- A. Numerous change requests
- B. To reduce redundancy
- C. Natural disaster
- D. Power fluctuation
Correct answer: A
Explanation
The correct answer is A, as multiple change requests can necessitate a revision of the baseline to accommodate new requirements or modifications. The other options, while they may impact project plans, do not directly relate to the formal process of changing a baseline.