Certified Authorization Professional (CAP) — Question 7

You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process. Which one of the following is NOT an output of the risk response planning?

Answer options

Correct answer: D

Explanation

The correct answer is D, as Organizational process assets updates are not a direct output of the risk response planning process. The other options, A, B, and C, represent legitimate outputs that are typically produced during this phase of project management.