Certified Authorization Professional (CAP) — Question 1

You are the project manager of the NKQ project for your organization. You have completed the quantitative risk analysis process for this portion of the project.
What is the only output of the quantitative risk analysis process?

Answer options

Correct answer: D

Explanation

The only output of the quantitative risk analysis process is the risk register updates, which document the identified risks and their quantitative analysis. The other options, while relevant to risk management, do not specifically represent the direct output of this analysis phase.