The BEST control to mitigate the risk associated with project scope creep is to:

Answer options

Correct answer: B

Explanation

Implementing change management procedures is crucial as it allows for a structured approach to handle modifications, ensuring that all changes are assessed and approved before being implemented. The other options, while helpful in their own right, do not directly address the control of scope changes as effectively as a formal change management process.