Which of the following is MOST likely to cause a key risk indicator (KRI) to exceed thresholds?
Answer options
- A. Risk scenarios
- B. The risk tolerance level
- C. A performance measurement
- D. Occurrences of specific events
Correct answer: D
Explanation
Occurrences of specific events are direct triggers that can lead to changes in risk levels, thereby causing a KRI to exceed its thresholds. In contrast, risk scenarios and risk tolerance levels are more about assessment and benchmarks, while performance measurements are typically used to track efficiency, not risk thresholds.