Certified in Risk and Information Systems Control (CRISC) — Question 911
Which of the following is MOST important when conducting a post-implementation review as part of the system development life cycle (SDLC)?
Answer options
- A. Verifying that project objectives are met
- B. Reviewing the project initiation risk matrix
- C. Identifying project cost overruns
- D. Leveraging an independent review team
Correct answer: A
Explanation
The correct answer, A, emphasizes the importance of confirming that the project's objectives have been successfully accomplished, which is vital for assessing overall project success. Options B, C, and D, while relevant, do not capture the primary focus of the review, which is to ensure that the initial goals were met.