Certified in Risk and Information Systems Control (CRISC) — Question 892
A risk practitioner is utilizing a risk heat map during a risk assessment. Risk events that are coded with the same color will have a similar:
Answer options
- A. risk response.
- B. risk impact.
- C. risk likelihood.
- D. risk score.
Correct answer: D
Explanation
The correct answer is D, as risk heat maps use colors to represent different levels of risk scores, which combine both likelihood and impact. Options A, B, and C do not correspond to the coding system of a heat map but rather represent other aspects of risk management that may not share the same color designation.