Certified in Risk and Information Systems Control (CRISC) — Question 863

Which of the following is the BEST control to minimize the risk associated with scope creep in software development?

Answer options

Correct answer: A

Explanation

The correct answer is A, as having a structured procedure for managing project changes helps to formally evaluate and control changes to the project scope, thereby minimizing scope creep. Options B and C, while important, do not directly address the management of project scope changes. Option D relates to testing processes but does not help in controlling scope creep.