Certified in Risk and Information Systems Control (CRISC) — Question 863
Which of the following is the BEST control to minimize the risk associated with scope creep in software development?
Answer options
- A. An established process for project change management
- B. Business management's review of functional requirements
- C. Segregation between development, test, and production
- D. Retention of test data and results for review purposes
Correct answer: A
Explanation
The correct answer is A, as having a structured procedure for managing project changes helps to formally evaluate and control changes to the project scope, thereby minimizing scope creep. Options B and C, while important, do not directly address the management of project scope changes. Option D relates to testing processes but does not help in controlling scope creep.