Certified in Risk and Information Systems Control (CRISC) — Question 820

What is the PRIMARY benefit of risk monitoring?

Answer options

Correct answer: C

Explanation

The correct answer, C, highlights that monitoring risks helps decision-makers consider potential risks when making choices. While A, B, and D are valid aspects of risk management, they do not primarily capture the essence of what risk monitoring achieves in terms of informed decision-making.