What is the PRIMARY benefit of risk monitoring?
Answer options
- A. It facilitates communication of threat levels.
- B. It provides statistical evidence of control efficiency.
- C. It facilitates risk-aware decision making.
- D. It reduces the number of audit findings.
Correct answer: C
Explanation
The correct answer, C, highlights that monitoring risks helps decision-makers consider potential risks when making choices. While A, B, and D are valid aspects of risk management, they do not primarily capture the essence of what risk monitoring achieves in terms of informed decision-making.