Certified in Risk and Information Systems Control (CRISC) — Question 811
Which of the following is the MOST important objective of embedding risk management practices into the initiation phase of the project management life cycle?
Answer options
- A. To deliver projects on time and on budget
- B. To assess inherent risk
- C. To assess risk throughout the project
- D. To include project risk in the enterprise-wide IT risk profile
Correct answer: C
Explanation
The correct answer is C because assessing risk throughout the project ensures that risks are identified and managed at every stage, leading to better project outcomes. Options A and B focus on specific aspects of risk and project delivery, while D pertains to a broader IT perspective that may not be the primary focus during the initiation phase.