Certified in Risk and Information Systems Control (CRISC) — Question 646
The BEST metric to monitor the risk associated with changes deployed to production is the percentage of:
Answer options
- A. changes not requiring user acceptance testing.
- B. changes that cause incidents.
- C. changes due to emergencies.
- D. personnel that have rights to make changes in production.
Correct answer: B
Explanation
The correct answer is B because monitoring the changes that cause incidents directly reflects the impact of deployments on system stability. Options A, C, and D do not provide a clear indication of the operational risk associated with the changes themselves.