Certified in Risk and Information Systems Control (CRISC) — Question 60
Which of the following is true for Cost Performance Index (CPI)?
Answer options
- A. If the CPI > 1, it indicates better than expected performance of project
- B. CPI = Earned Value (EV) * Actual Cost (AC)
- C. It is used to measure performance of schedule
- D. If the CPI = 1, it indicates poor performance of project
Correct answer: A
Explanation
The correct answer, A, is accurate because a CPI greater than 1 indicates that the project is performing more efficiently than planned. Option B is incorrect as the formula for CPI is actually CPI = EV / AC. Option C is false since CPI specifically measures cost performance, not schedule. Option D is misleading because a CPI of 1 indicates that the project is on budget, not poor performance.