Certified in Risk and Information Systems Control (CRISC) — Question 526
Which of the following is MOST important for senior management to review during an acquisition?
Answer options
- A. Key risk indicator (KRI) thresholds
- B. Risk framework and methodology
- C. Risk communication plan
- D. Risk appetite and tolerance
Correct answer: D
Explanation
The correct answer, D, highlights the significance of understanding the organization's risk appetite and tolerance to ensure alignment with strategic goals during an acquisition. While the other options are important, they are more about processes and frameworks rather than the overarching risk stance that senior management needs to prioritize.