Certified in Risk and Information Systems Control (CRISC) — Question 484
Which of the following is the BEST key performance indicator (KPI) to measure how effectively risk management practices are embedded in the project management office (PMO)?
Answer options
- A. Reduction in audits involving external risk consultants
- B. Percentage of projects with key risk accepted by the project steering committee
- C. Percentage of projects with developed controls on scope creep
- D. Reduction in risk policy noncompliance findings
Correct answer: B
Explanation
The correct answer, B, focuses on the approval of key risks by the project steering committee, indicating that risk management practices are being actively considered and integrated into decision-making. Options A and D relate to audits and compliance findings but do not directly measure the effectiveness of risk management integration. Option C, while relevant to project management, does not specifically address the acceptance of key risks.