Certified in Risk and Information Systems Control (CRISC) — Question 481

You are the project manager in your enterprise. You have identified risk that is noticeable failure threatening the success of certain goals of your enterprise. In which of the following levels do this identified risk exists?

Answer options

Correct answer: B

Explanation

The correct answer is 'High risk' because the question specifies that the identified risk is a noticeable failure that threatens the success of certain goals. The other options, such as 'Moderate', 'Extremely high', and 'Low risk', do not accurately reflect the severity indicated in the scenario.